Power is the one part of a garden office that is genuinely awkward to retrofit. Insulation, cladding and flooring all come back off comparatively easily; a buried cable does not. So before the base goes down, work out what you actually intend to run – and then assume you will run more.
A typical day might involve a laptop, two monitors, a desk lamp, a printer, a kettle and a 2kW heater. That lot will happily draw close to 13 amps, and if you add a small air conditioning unit or a treadmill desk, you are into a different league entirely. Add up the wattages, convert to amps (watts divided by 230), and give yourself at least 50 per cent headroom.
Measure the cable route properly, too. The distance that matters is the length of the run round the flower bed, not the straight line across the lawn. Long runs lose voltage, and your electrician will need that figure to size the cable correctly.
Any supply that leaves the house should be run in steel wire armoured (SWA) cable, buried at least 450mm deep and ideally protected by a duct with warning tape above it. The duct is worth the small extra cost: it lets you pull a second cable through later without digging anything up.
The office should have its own small consumer unit with residual current device protection – not a spur taken off a ring main, and never an extension lead trailed across the patio. In England and Wales, new circuits supplying an outbuilding are notifiable work under Part P of the Building Regulations, so use a registered electrician who can test, certify and notify it. The rules differ in Scotland and Northern Ireland, so check locally before you start.
One more thing while the trench is open: run a draw cord through it. Future you will be grateful.
Where sockets go matters even more than how many you fit – though fit plenty. On a desk wall, position twin sockets roughly 150mm above the worktop so chargers and monitor plugs sit behind the screens rather than under your feet. Keep them clear of where a monitor arm or shelving will eventually be fixed.
Floor-level sockets suit a central desk, but raise them on a small upstand to keep them clear of spills and damp mops.
Wi-Fi that has to cross a garden wall, a patio and an insulated stud wall is rarely reliable enough for video calls all day. If you possibly can, run a Cat6 cable from the router to the office alongside the power, terminating in a wall plate with two or three ports. Even if you use wireless most of the time, a hardwired connection at the desk gives you a fallback and noticeably lower latency.
If digging is not an option, a mesh system with a node in the office, or a point-to-point wireless link, can work well – but both depend on clear line of sight. Whatever you choose, keep data and mains cables in separate ducts where possible, and never run them tightly together through the same hole. Safety and signal quality both suffer otherwise.
Good lighting in a garden office is really three separate jobs. Task lighting illuminates the keyboard or paperwork in front of you, ambient lighting fills the room so your eyes are not straining against a bright screen, and daylight does the rest.
Skylights and a well-placed window do more than any fitting, but plan blinds for the months when low sun hits the monitor directly.
Lighting and power only feel complete once the room is comfortable. A thermostatically controlled panel heater or a small air source heat pump takes the edge off without the running costs of a fan heater, and a ceiling fan on its summer setting moves air far more cheaply than air conditioning. Ventilation matters as well – a well-sealed hut gets stuffy within an hour, so allow a trickle vent or an extract fan.
Finally, have the installation tested and certified, and keep the paperwork with your house documents. Ask for a schedule of circuit details and a note of when the next inspection is due. If you ever sell the property, that certificate is exactly what a surveyor will ask to see.